Trace each packed module from the island terminal to the bottling room. Record the dimensions supplied by the packer and use photographs or measurements for each change of vehicle, route or custody. Ask the carrier and the plant to confirm the actual access window.
Copy a port-to-room route sheet
| Leg | Evidence to collect | Decision |
|---|---|---|
| Terminal and collection | Named arrival and receiving party, recorded package outline and photo reference | Confirm when the assigned vehicle can collect |
| On-island storage or transfer | Approved storage conditions and responsibility during delay | Keep a staged option if arrival misses the site window |
| Gate and line room | Measured openings, corners, obstructions and service space | Have qualified crews confirm a route for each crate |
| Handover | Installed orientation and owner | Confirm when the space is available to receive it |
If a late ferry would arrive after site access closes, confirm custody and approved storage before dispatch. Include the actual crate outline, mass and site arrival date in the handling enquiry.
Use the Greek site delivery guide to coordinate island transport with documented route conditions and installation.